Example brief
A construction-to-commissioning Gantt for a 150 MW solar farm that isolates the critical path - interconnection approval, civil works, install, and commissioning - as one dominant chain, with permitting and procurement shown as supporting context. The message is that grid interconnection approval gates every downstream task and protects the August energization date.
Render it
Brief path
curl -X POST https://api.slideforge.dev/v1/render/auto \
-H "Authorization: Bearer sf_live_..." \
-H "Content-Type: application/json" \
-d '{ "brief": "A construction-to-commissioning Gantt for a 150 MW solar farm that isolates the critical path - interconnection approval" }'Structured intent (this template)
{
"pattern": "gantt_plan",
"title": "Grid interconnection approval is the critical path to energizing the solar farm",
"subtitle": "150 MW Vale Verde solar - construction-to-commissioning plan",
"variant": "critical_path_gantt",
"periods": [
"Mar",
"Apr",
"May",
"Jun",
"Jul",
"Aug"
],
"tasks": [
{
"id": "permit",
"label": "Permitting & land lease",
"start": "Mar",
"end": "Apr"
},
{
"id": "interconnect",
"label": "Interconnection study & approval",
"start": "Mar",
"end": "May",
"emphasis": "primary"
},
{
"id": "procure",
"label": "Module & inverter procurement",
"start": "Apr",
"end": "Jun"
},
{
"id": "civil",
"label": "Site civil & foundations",
"start": "May",
"end": "Jun",
"emphasis": "primary"
},
{
"id": "install",
"label": "Panel & inverter install",
"start": "Jun",
"end": "Jul",
"emphasis": "primary"
},
{
"id": "commission",
"label": "Commissioning & energization",
"start": "Jul",
"end": "Aug",
"emphasis": "primary"
}
],
"dependencies": [
{
"from": "interconnect",
"to": "civil"
},
{
"from": "civil",
"to": "install"
},
{
"from": "install",
"to": "commission"
}
],
"milestones": [
{
"label": "Energization",
"period": "Aug",
"emphasis": "primary"
}
],
"today": "May",
"takeaway": "Interconnection approval gates every downstream task - protect that date above all.",
"source_note": "Commissioning plan rev C, 2026"
}Related templates
Bars vs target marker
Margin recovery is visible but three units are below target
Diverging variance bars
Cloud hosting and contractor spend offset hiring delay savings
Ranked magnitude bars
Three offer families drive 68% of FY25 growth
Stacked composition bars
Compare media mix for FY25 and FY26
Frequently asked questions
How do I render the Critical path gantt template?
Send a POST to /v1/render/auto with a brief, or call create_slide via MCP with the structured intent shown below. The response includes an editable .pptx, a PDF, and a PNG. $0.05 per slide.
Does an AI write the slide?
No. SlideForge renders deterministically from a structured intent — no LLM draws the slide, so text is never mangled or fabricated. The optional brief path uses a router to pick the pattern, then renders deterministically.
Can I customize the colors and fonts?
Yes. Pass a theme_id to apply a built-in or custom brand theme; the layout stays the same.
Try this template
Render Critical path gantt deterministically — editable PowerPoint in under a second.